X-energy Reports Third Quarter 2026 Results
Revenues and grant income of $66.3 million, compared to revenues and grant income of $30.4 million in 3Q 2025
Dow and X-energy receive Construction Permit from Nuclear Regulatory Commission (“NRC”) ahead of schedule
Selects Fluor Corporation (“Fluor”) to advance nuclear engineering and design for second Xe-100 project
Announced first procurement order with Alleima and Doosan Enerbility for long-lead steam generator components
Announced Joint Development Agreement (“JDA”) with American Electric Power (“AEP”) to advance feasibility work for a proposed 960 MW Xe-100 small modular reactor (“SMR”) project in Indiana
Xe-100 SMR accepted into the United Kingdom’s Generic Design Assessment (“GDA”) process
Vertical construction of TX-1 fuel fabrication facility complete, project advances into the next phase which will include interior buildout, equipment installation and construction of supporting facilities
Strong balance sheet with $1.8 billion in total liquidity, consisting of $1.0 billion in cash and cash equivalents, $0.5 billion in short-term investments and $0.3 billion in long-term investments, and zero debt outstanding
ROCKVILLE, Md., November 12, 2026 – X-Energy, Inc. (Nasdaq: XE) (“X-energy” or the “Company”), a leading developer of advanced nuclear reactors and fuel technology, today announced third quarter 2026 financial results and operational highlights.
“Our third quarter results and recent project developments reflect meaningful progress in executing our strategy and advancing our technology toward commercial deployment.
We are building momentum as we deepen relationships with leading energy and industrial companies and advance opportunities across our pipeline,” said J. Clay Sell, CEO of X-energy.
“The NRC recently issued the construction permit for Dow’s Long Mott project in Texas and it was received over a month ahead of schedule.
This marks the first construction permit issued by the NRC in the United States for an advanced nuclear project site designed to provide industrial process heat.”
“Furthermore, we are excited to collaborate with AEP, a major investor-owned utility with extensive experience and expertise developing and operating critical energy infrastructure.
This project in Indiana represents our second announced commercial deployment opportunity supported by Amazon and gives us greater visibility into our path toward deployment.
During the quarter, we also completed the vertical construction of our TX-1 fuel fabrication facility, and the next phase includes interior buildout and equipment installation.
5In addition, the acceptance of our Xe-100 reactor into the United Kingdom’s Generic Design Assessment process represents an important step toward advancing our opportunity in the U.K. with Centrica. ”
“We are in a differentiated position of strength, supported by our strong balance sheet and significant funding.
Our regulatory progress marks a major milestone for our technology, while our growing commercial momentum bolsters our pipeline of reactors and demand for TRISO-X fuel,” concluded Sell.
Operational Highlights
NRC Issues Construction Permit for Dow’s Long Mott Project: Dow and X-energy announced that the NRC has approved the Construction Permit Application (“CPA”) for the proposed Long Mott Generating Station in Seadrift, Texas ahead of schedule.
The permit marks an important milestone in the regulatory review process for
the proposed advanced nuclear project, which is being developed under the U.S. Department of Energy's Advanced Reactor Demonstration Program (“ARDP”).
The project is intended to provide zero-carbon emissions electricity and high-temperature steam to Dow's Seadrift Operations site, replacing existing energy and steam assets near their end-of-life.
The NRC's approval follows a comprehensive review of the proposed facility, site characteristics, construction plans, environmental considerations and safety-related information submitted as part of the CPA process.
6Issuance marks the first NRC CPA approval of a high-temperature gas-cooled reactor (“HTGR”) in nearly 60 years, the first-ever pebble-bed HTGR approval and the first-ever for an advanced nuclear industrial deployment.
Selects Fluor for Design and Engineering Services: For Energy Northwest’s Cascade Advanced Energy Facility near Richland, Washington, Fluor will provide engineering, design development, supply chain, estimating and project controls services for the areas of the plant containing the Xe-100 reactors and the systems that support them (the "nuclear island").
The agreement between X-energy and Fluor represents their second commercial contract for nuclear island engineering and design, building on Fluor's ongoing work for the Company’s first proposed Xe-100 project in Texas under the ARDP.
This enables X-energy and Fluor to incorporate learnings from one project into the next, with the aim of targeting long-term cost and schedule reductions through standardization and highly repeatable project execution.
Executes First Order for Steam Generator Components: Announced the first procurement order of steam generator tubing from Alleima and Doosan Enerbility for the Company’s Xe-100 advanced SMR.
This follows the signing of a strategic framework by the three companies earlier this year as the Company scales its supply chain to meet its growing commercial pipeline.
1Execution advances a safety-significant, long-lead component for the first deployment of the Xe-100.
Alleima will leverage its expertise in high-temperature alloys to manufacture specialized steel tubing, which Doosan will bend into helical coils using its proprietary fabrication processes.
These coils are a central component of the Xe-100 steam generator, safely removing heat to produce high-temperature steam at up to 565°C, and allowing a single Xe-100 to deliver both electricity and high-temperature process heat for industrial applications.
Partners with AEP and Amazon : Announced a JDA with AEP to advance feasibility work for a proposed 960 MW Xe-100 SMR project in Indiana.
Amazon will provide certain project development funding for the effort, marking the second commercial deployment opportunity under X-energy and Amazon’s collaboration aimed to bring more than 5 GW of new nuclear capacity to the U.S. grid by 2039.
X-energy and AEP will evaluate the development of a 12-unit Xe-100 plant in Sullivan County, Indiana.
The proposed project would redevelop the AEP-owned brownfield site for advanced nuclear power, adding clean baseload capacity to help meet growing demand for safe, reliable energy.
8U.K. Regulators Begin Design Review for Xe-100: The U.K. Government has directed regulators to accept the Xe-100 reactor for design review and advance X-energy’s and Centrica’s efforts to deploy up to 6 GW of new nuclear in the U.K. GDA acceptance formally triggers the process of assessing the design's acceptability for deployment and operation ahead of the technical and environmental evaluations required for site-specific licensing and permitting.
The assessment is expected to take approximately three years and will be administered by the U.K. Office for Nuclear Regulation, the Environment Agency, and Natural Resources Wales.
The submission builds on the Xe-100's U.S. licensing progress and is expected to benefit from expanded collaboration between the U.K. regulators and the U.S. NRC, enabling transfer of NRC-reviewed design documentation and safety analyses into U.K. design reviews.
TX-1 Vertical Construction Complete, Advances to Next Phase : Vertical construction for the shell of the Company's TX-1 fuel facility in Oak Ridge, Tennessee was completed on schedule in the third quarter.
The project has advanced into its next phase of construction, which will include interior buildout, installation of fuel fabrication equipment and continued construction of supporting facilities.
Once operational, TX-1 is expected to produce approximately 700,000 TRISO-X fuel pebbles annually, equivalent to 5 metric tons of uranium (“MTU”), with capacity to provide fuel for up to 11 Xe-100 reactors.
2The U.S. NRC granted TRISO-X a 40-year Special Nuclear Material License covering the facility earlier this year, the first-ever NRC Category 2 fuel fabrication license issued for the processing of high-assay low-enriched uranium.
TX-1 is expected to be the first new commercial-scale advanced U.S. nuclear fuel fabrication facility built in more than 50 years.
Financial Results
Total revenues and grant income in the three months ended September 30, 2026 were $66.3 million, including $51.5 million of services revenue and $14.8 million of grant income.
Total revenues and grant income in the nine months ended September 30, 2026 were $164.4 million, including $141.6 million of services revenue and $22.8 million of grant income.
Total revenues and grant income increased 118% and 126% for the three and nine months ended September 30, 2026, respectively, compared to the comparable prior-year period.
This was primarily due to increases of $29.3 million and $85.0 million in revenue and grant income from the ARDP Agreement with the DOE for the three and nine months ended September 30, 2026, respectively.
This was driven by an increase in project execution activities under the ARDP Agreement as the Company continued to advance the development and finalization of the Xe-100 reactor design.
The increase reflected higher spending on materials, subcontractor services, and compensation costs to support the expanded scope of work.
Total operating expenses in the three months ended September 30, 2026 were $169.9 million, including $93.6 million of Direct costs.
Total operating expenses in the nine months ended September 30, 2026 were $444.1 million, including $245.6 million of Direct costs.
Total operating expenses increased 139% and 143% for the three and nine months ended September 30, 2026, respectively, compared to the comparable prior-year periods.
This was primarily due to increases of $54.7 million and $141.9 million in Direct costs and increases of $43.9 million and $120.4 million in Selling, general, and administrative expenses for the three and nine months ended September 30, 2026, respectively, compared to the comparable prior-year periods.
The increase in Direct costs was primarily driven by expanded activity under the ARDP Agreement.
Subcontracting costs increased by $23.5 million and $52.8 million for the three and nine months ended September 30, 2026, respectively.
Direct materials costs increased $15.6 million and $33.3 million for the three and nine months ended September 30, 2026, respectively.
Additionally, compensation costs increased by $15.3 million and $53.0 million for the three and nine months ended September 30, 2026, respectively, including $10.9 million and $42.0 million from higher employee headcount to support the expanded activity under the ARDP Agreement, and $4.4 million and $11.0 million from increased non-cash equity-based and unit-based compensation expense for the three and nine months ended September 30, 2026 due to equity grants to certain former holders of Profits Interest Units (“PIUs”) in connection with the Company’s IPO in April.
The increase in Selling, general, and administrative expenses was driven by an increase in non-cash equity-based and unit-based compensation expense of $18.4 million and $49.2 million for the three and nine months ended September 30, 2026, respectively, due to the equity grant to certain PIU holders discussed above.
Compensation costs increased a further $9.0 million and $29.4 million for the three and nine months ended September 30, 2026, respectively, primarily due to higher employee headcount.
Additionally, infrastructure and professional service costs increased by $8.0 million and $23.8 million for the three and nine months ended September 30, 2026, respectively.
7Selling, general and administrative expenses increased a further $8.5 million and $12.0 million for the three and nine months ended September 30, 2026, respectively, from contractor costs related to corporate projects, including design costs for TX-2.
Net cash used in operating activities in the nine months ended September 30, 2026 was $215.8 million of net cash compared to $92.7 million for the nine months ended September 30, 2025.
The increase in cash used in operating activities is primarily driven by increases in activity on the ARDP Agreement, deposits to vendors for long-lead materials, and corporate headcount and corporate contractors during the nine months ended September 30, 2026 compared to the nine months ended September 30, 2025.
Net cash used in investing activities in the nine months ended September 30, 2026 was $289.5 million of net cash compared to $41.8 million for the nine months ended September 30, 2025.
The increase in net cash used in investing
activities was attributable to investments in held-to-maturity securities and capital expenditures.
During the nine months ended September 30, 2026, we purchased investments of $425.3 million, which were offset by proceeds from investment maturities of $233.9 million.
There was no investment activity during the nine months ended September 30, 2025.
During the nine months ended September 30, 2026, compared to the corresponding prior year period, we had a $98.8 million increase in capital expenditures related to the construction of facilities, which was offset by a $42.5 million increase in reimbursements received for the capital expenditures qualifying under government grant programs.
Net cash provided by financing activities in the nine months ended September 30, 2026 was $1.1 billion of net cash compared to $50.2 million for the nine months ended September 30, 2025.
The net cash provided by financing activities during the nine months ended September 30, 2026 was primarily due to $1.1 billion of net proceeds from X-energy’s initial public offering.
The net cash provided by financing activities during the nine months ended September 30, 2025 was primarily due to the January 2025 issuance of Series C-1 preferred units of $53.4 million, offset by $2.5 million of cash paid for associated issuance costs.
Liquidity
Cash and cash equivalents totaled $1.0 billion as of September 30, 2026.
Short-term investments totaled $514.3 million and Long-term investments totaled $247.1 million, for total liquidity of $1,805.5 million as of September 30, 2026.
The Company had no debt outstanding as of September 30, 2026 and December 31, 2025.
Project Pipeline
The Company’s expected project pipeline consists of 144 reactors with three announced commercial Xe-100 projects in the U.S. and the fourth announced in the U.K. for approximately 11.5 gigawatts electric, assuming each customer exercises its contingent rights in full.
X-energy has high-quality customers and partners across its four existing projects with Dow, Amazon/Energy Northwest, Centrica and Amazon/American Electric Power, who are expected to underpin the deployment of the initial fleet of Xe-100 reactors.
Participation in Upcoming Investor Conferences
X-energy is scheduled to participate in the following upcoming events:
UBS Global Technology and AI Conference, November 30, 2026, Scottsdale, AZ
Truist Virtual Nuclear Summit, December 10, 2026 (virtual)
Stifel Frontier Tech 2.0 Energy Summit, December 10, 2026, New York, NY
Jefferies Power, Energy, Utilities, Clean & Pipes Conference, March 2, 2027, New York, NY
X-energy is a leading designer of advanced small modular nuclear reactors (“SMR”) and fuel technology developed to
establish a new standard in clean, safe, reliable energy.
4X-energy's intrinsically safer Xe-100 high-temperature gas-cooled reactor and TRISO-X particle fuel expand applications for nuclear technology, with commercial projects across grid, industrial, and AI.
Together, X-energy's technology drives enhanced safety, lower cost, faster construction timelines, and scalable deployment when compared with other SMRs and conventional nuclear.
For more information, visit X-energy.com or connect with us on X or LinkedIn .
Such statements can be identified by the fact they do not relate strictly to historical or current facts.
3Actual results may differ materially as a result of a number of factors, including, without limitation, the Company’s ability to achieve final investment decisions from its customers; ability to realize its plans to deliver a commercial Xe-100; the Company’s projects may be subject to delays or setbacks, increasing costs or termination; the risk that customers do not exercise their contingent rights in full; its liquidity and ability to raise capital; changes or delays in support from the U.S. government, including ARDP and expected modification; changes, delays, or an inability to receive licenses or other governmental approvals necessary for X-energy’s reactors and fuel facilities; uncertainty and changes in expected costs, schedules and unit economics due to inflation; supply chain constraints (including access to HALEU, tubing, graphite and certain other materials), including suppliers inability to fulfill their contractual obligations; the Company’s minimum purchase and prepayment commitments; reliance on a limited number of specialized suppliers and exposure to supply disruptions, quality issues, and trade policy changes; labor availability, site-specific factors and first-of-a-kind risks; X-energy’s limited operating experience at intended scale and the possibility that latent design or operational issues may emerge; safety, security, and cybersecurity incidents; the nascent and uncertain market adoption of SMRs and the possibility that demand may grow more slowly than expected or customers may defer or cancel projects; competition from competitors with potentially greater resources or lower costs; reliance on key partners and customers, including Amazon’s support on multiple projects, and the risk that changes in partner or customer priorities or timelines
could materially affect commercialization; customer contractual terms that may constrain capacity allocation and compress margins; licensing and scaling X-energy’s fuel fabrication campus and delays in licensing or facility construction; general economic conditions; changes in laws, regulations, incentives, energy market rules, export controls, or government policies; shifts in public perception and political support for nuclear energy or Company customers; dependence on key personnel and ability to hire and retain talent; and ability to obtain, maintain, or enforce IP rights.
The foregoing list of factors is not exhaustive.
Additional information concerning these and other factors can be found in the section entitled “Risk Factors” in X-energy’s most recent Form 10-Q filed with Securities and Exchange Commission (“SEC”), and in subsequent filings made with the SEC.
Due to known and unknown risks, X-energy’s results may differ materially from its expectations and projections.
This press release presents information about certain non-GAAP financial measures.
Because of this and other limitations, you should not consider the non-GAAP financial measures as a substitute for GAAP-based financial performance measures.
Reconciliations of these non-GAAP financial measures to the most directly comparable GAAP financial measures are provided herein.